WORKDAY Function

The WORKDAY function in Excel is used to calculate the date of a working day that is a specified number of working days before or after a start date. By default, it excludes weekends (Saturday and Sunday) and can also exclude any specified holidays. This function is helpful for project management and date-based scheduling tasks.

Syntax

WORKDAY(start_date, days, [holidays])
  • start_date: A valid Excel date representing the starting point for the calculation.
  • days: The number of working days to add (positive) or subtract (negative) from start_date.
  • [holidays] (optional): An optional range or array of dates representing non-standard workdays (e.g., public holidays) to exclude.

Returns

The WORKDAY function returns a date that is the calculated working day, adjusted to exclude weekends and any specified holidays.

Key Features

  • Date Projection: Useful for calculating future or past business days from a given date, helping in planning deadlines or setting completion dates.
  • Customizable Holidays: Allows you to exclude additional dates (e.g., public holidays) beyond the standard weekends for an accurate calculation.

Example

Example 1: Basic Usage

Suppose you want to calculate the date 10 working days after 01-Jan-2024.

=WORKDAY(DATE(2024, 1, 1), 10)

This formula will return 15-Jan-2024, skipping weekends.


Example 2: Including Holidays

Now, suppose 01-Jan-2024 (New Year's Day) is a public holiday. You can specify it as a holiday in the WORKDAY function.

=WORKDAY(DATE(2024, 1, 1), 10, {DATE(2024, 1, 1)})

This formula will return 16-Jan-2024, adjusting for the holiday in addition to the weekends.


Example 3: Using a Cell Range for Holidays

If holiday dates (e.g., 01-Jan-2024, 06-Jan-2024, and 13-Jan-2024) are listed in cells A1:A3, you can reference them:

=WORKDAY(DATE(2024, 1, 1), 10, A1:A3)

This formula will account for all holidays in the range A1:A3 and adjust the result accordingly.


Example 4: Calculating with Negative Days

To calculate 10 working days before 15-Jan-2024:

=WORKDAY(DATE(2024, 1, 15), -10)

This formula will return 01-Jan-2024, skipping weekends.

Notes

  • The start_date is counted only if it falls on a working day. Otherwise, the calculation begins from the next working day.
  • Dates provided for the holidays parameter must be valid Excel dates.
  • If the resulting date is adjusted into a weekend or holiday, the function will skip over it to the nearest working day.
  • Use the WORKDAY.INTL function for custom weekend definitions beyond the default Saturday-Sunday.

The WORKDAY function is an essential tool for planning and scheduling work projects, enabling you to calculate deadlines and milestones accurately while accounting for non-working days.